history NACC Project History

Journey of building our dream community from conception to reality

2020 Started

Project Progress

lightbulb

Phase 1 – Concept & Governance

Shared proposal with small group; formed ad-hoc committee; explored initial land option; identified need for additional land

Mar-22
lightbulb

Phase 1 – Concept & Governance

Registered NACC Investment Group, LLC in North Carolina

Apr-22
timeline

Phase 2 – Land Acquisition

Purchased initial 25 acres; created 63 shares sold to 55 members

May-22
timeline

Phase 2 – Land Acquisition

Purchased additional 6.5 acres; increased shares to 74

Aug-22
timeline

Phase 2 – Land Acquisition

Purchased additional 20 acres; total land exceeded 52 acres

May-23
timeline

Phase 3 – Member Alignment

Member survey conducted; increased share price and entry fee

Aug-23
timeline

Phase 3 – Member Alignment

Buy/sell round completed; total shares increased to 106

Dec-23
timeline

Phase 4 – Entitlements

Project approved by City of Mebane Planning Board

Aug-24
timeline

Phase 4 – Entitlements

Annexation and rezoning approved by City Council

Sep-24
timeline

Phase 5 – Membership Stabilization

Buy/sell round completed; shares stabilized

Oct-24
timeline

Phase 5 – Membership Stabilization

Buy/sell round completed; membership increased to 84

Dec-25
engineering

Phase 6 – Engineering Design

Estimated Phase I construction design approval

Mar-26
engineering

Phase 6 – Engineering Design

Estimated Phase II construction design approval

Jun-26
construction

Phase 7 – Pre-Construction

Bid tabulation, erosion control permits

Aug-26
construction

Phase 7 – Pre-Construction

Land developer bidding and selection

Oct-26
construction

Phase 8 – Construction

Land development and Phase I home construction begins

Jan-27
construction

Phase 8 – Construction

Phase II home construction begins

Jun-27
construction

Phase 8 – Construction

Phase III amenities construction begins

Jan-29
construction

Phase 8 – Construction

Estimated full project completion

Dec-29
Overall Progress: 0% Complete Currently in Planning Phase

Project Milestones Spreadsheet

NACC Project Milestones Spreadsheet
view_list

Detailed Timeline

View our complete project milestone spreadsheet

Key Milestones

lightbulb

Phase 1 – Concept & Governance

Shared proposal with small group; formed ad-hoc committee; explored initial land option; identified need for additional land

Mar-22
lightbulb

Phase 1 – Concept & Governance

Registered NACC Investment Group, LLC in North Carolina

Apr-22
timeline

Phase 2 – Land Acquisition

Purchased initial 25 acres; created 63 shares sold to 55 members

May-22
timeline

Phase 2 – Land Acquisition

Purchased additional 6.5 acres; increased shares to 74

Aug-22
timeline

Phase 2 – Land Acquisition

Purchased additional 20 acres; total land exceeded 52 acres

May-23
timeline

Phase 3 – Member Alignment

Member survey conducted; increased share price and entry fee

Aug-23
timeline

Phase 3 – Member Alignment

Buy/sell round completed; total shares increased to 106

Dec-23
timeline

Phase 4 – Entitlements

Project approved by City of Mebane Planning Board

Aug-24